Road and Trail Construction

Current Projects

State Road 32 Reconstruction

  • Schedule: Ongoing, substantial completion in Fall 2026
  • Details: Click Here

Old 146th Street & Towne Road Roundabout

  • Phase I completed in Fall 2025, Phase 2 will begin in Spring 2026
  • Duration – 45 days
  • Detour – 146th Street, Ditch Road, 151st Street
  • Contractor – Midwest Paving
  • Cost – Estimated $3,000,000

161st Street Trail (Oak Road to Carey Road)

  • Start Date – Fall 2025, will resume Spring 2026
  • Duration – Approximately 30 days remaining
  • Detour – No Closure
  • Contractor – E&B Paving
  • Cost – Estimated $250,000

171st Street & Ditch Road Roundabout

  • Started September 2025, will resume Spring 2026
  • Duration – Approximately two weeks of remaining work
  • Detour – Spring Mill, 161st Street, Ditch Road
  • Contractor – Valenti Held
  • Cost – $1,400,000

171st and Ditch Detour



Future Projects

Monon Tunnel

  • Start date – Spring 2026
  • Duration – Expected Completion December 2026
  • Detour – 161st Open to traffic, Monon Detour – 156th, Oak Ridge Road, 169th Street
  • Contractor – TBD
  • Cost – Estimated $8,000,000

191st Street Widening Phase I

Details: Widening of 191st Street from Tomlinson Road to Grand Park Boulevard, including a roundabout at Grand Park Boulevard and a pedestrian bridge for Monon over 191st.

  • Schedule: Utility Work Spring 2026, Roundabout Construction Fall 2026, Remaining Construction on 191st Street and Pedestrian Bridge Construction in Spring 2027
  • Design Firm: Lochmueller Group
  • Contractor: TBD
  • Estimated Project Cost: $15,500,000

Downtown Drainage Improvements

Details: Roads include Union, Cherry, and Roosevelt Streets and College Avenue

  • Schedule: Utility Work in 2026, Construction in 2026-2027
  • Design Firm: VS Engineers
  • Contractor: TBD
  • Total Estimated Project Cost: $3,000,000
  • Funded by ARPA

Westfield Boulevard Phase II

Details: Connection from Lantern Commons to David Brown Drive including a roundabout at David Brown Drive

  • Schedule: Roundabout Construction in Fall 2026, Roadway Construction on Westfield Boulevard in Spring 2027
  • Design Firm: WSP
  • Contractor: TBD
  • Total Estimated Project Cost: $6,300,000

181st Street & Grand Park Boulevard Roundabout

  • Start Date – April 4, 2026
  • Opening Date – June 4, 2026
  • Design Firm: DLZ
  • Contractor: TBD
  • Total Estimated Project Cost: $2,000,000
  • Final Completion – September 2026

Mule Barn Road Widening

  • Start Date – Summer 2026
  • Design Firm - BF&S
  • Contractor – TBD
  • Detour – TBD
  • Cost – Estimated $2,000,000

151st Street Trail (Oak Road to Bridlewood Subdivision)

  • Start Date – Summer 2026
  • Duration – TBD
  • Detour – TBD
  • Contractor – TBD
  • Cost – Estimated $900,000

Penn Street Extension

  • Start Date – August 1, 2026
  • Duration – 60 Days
  • Contractor – E&B Paving
  • Total Estimated Project Cost – $650,000

Grand Park Boulevard & Tournament Trail Traffic Signal

  • Start Date – Spring/Summer 2026
  • Duration – 30 days
  • Contractor – TBD
  • Total Estimated Project Cost – $400,000

Grand Park Boulevard & John Dippel Boulevard Roundabout

  • Estimated Start Date – Spring 2027
  • Duration – TBD
  • Design Firm – VS Engineering
  • Contractor – TBD
  • Total Estimated Project Cost – $2.2m

151st Street Raised Crosswalk (151st Street & American Lotus Drive)

  • Estimated Start Date – Spring 2026
  • Duration – Two Weeks
  • Detour – Ditch Road, 146th Street, Towne Road

2026 Resurfacing Program

  • Estimated Start Date – April 2026
  • Completion – September 2026
  • Contractor – TBD
  • Total Estimated Project Cost – $3,000,000

2026 Concrete Patching Program

  • Estimated Start Date – March 2026
  • Completion – June 2026
  • Contractor – TBD
  • Total Estimated Project Cost – $300,000

Capital Improvement Plan

The Capital Improvement Plan is a working document through 2032 to outline infrastructure improvement projects. 

View the Capital Improvement Plan here


Completed Projects

161st Street & Spring Mill Road Roundabout (includes pedestrian bridge over John Edwards Drain)

  • Start Date – Approximately April 25, 2025
  • Duration – 60 days (full closure)
  • Detour – 156th St, Oak Ridge Road or Ditch Road, 169th/171st Street
  • Contractor – Morphey Construction
  • Cost – $3,590,000.00
  • Final Completion - September 10, 2025

151st Street & Towne Road Roundabout

  • Start Date – No later than April 7, 2025
  • Duration – 80 days (full closure)
  • Detour – 146th Street, Ditch Road, 156th St
  • Contractor – Midwest Paving
  • Cost – $1,983,669.69
  • Final Completion - September 30, 2025

181st Street & Wheeler Road Roundabout

  • Start Date – No earlier than May 27, 2025
  • Duration – 45 days (full closure)
  • Detour – 186th Street, Grand Park Boulevard, SR 32
  • Contractor – Calumet
  • Cost – $1,386,000.00
  • Substantial Completion - October 3, 2025
  • Final Completion - June 4, 2026

2025 Concrete Patching (Bridlewood Subdivision)

  • Start Date – between Mid-March and Mid-April
  • Duration – Completed by May 30th
  • Detour – No closure
  • Contractor – Midwest Paving
  • Cost – $145,812.27

Updated 09/14/2025